Hello all, Iam new to this forum and need a little help here as I'm a basic Primavera user.
I have created the WBS & the Activities successfully and I finished the predecessors, so the last remain step is to finalize the resources. I added the required resources to the resources list which include materials & labors, now I want to make the price/unit for each labor is per day not per hour as it's appear by default price/hr, how can I manage to do so?
Another thing, when adding resources to activities, I need to add more than 1 labor for each activity, for example 2 or 3 workers for each activitiy.........I got to acitivites then I clicked add resource from the bottom, the list of resources I added lately appeared, I go to with my mouse on each activitiy then I double click on the reource type I need to assign with the acitivity, but how could I manage to add 2 or 3 or 4? it's not logic to double clikc for three times on each labor to assgin 3 workers in each activitiy. Please advise.
Thank you.