Importing including relationship from Excel to P6.

4 replies [Last post]
abbas india
User offline. Last seen 13 years 39 weeks ago. Offline
Joined: 12 Jul 2009
Posts: 35

Hi all,

Anybody can help me to import activities with relationship from excel to P6.

Is it possible?

Kindly update me.

 

Regards,

Abbas

Replies

jeoffrey reyes
User offline. Last seen 4 years 17 weeks ago. Offline
Joined: 19 Jun 2008
Posts: 214

SDK is also using an excel file but with macro on it. you can try what stuart is suggesting for a simple excel import-export.

 

cheers,

Stuart Corbett
User offline. Last seen 5 years 24 weeks ago. Offline
Joined: 10 Feb 2009
Posts: 10

It is very easy. the quickest way is to do a blank export from Primavera and just use that as a template

abbas india
User offline. Last seen 13 years 39 weeks ago. Offline
Joined: 12 Jul 2009
Posts: 35

 

Hi Jeff,

So are you saying using normal excel file we cannot import activity relationship information from Microsoft Excel

Can you guide me how to get SDK and how to use it?

Kindly update me.

Regards,

Abbas

jeoffrey reyes
User offline. Last seen 4 years 17 weeks ago. Offline
Joined: 19 Jun 2008
Posts: 214

hi abbas,

 

possible....you can use SDK for that...

cheers,