Project tab - Summarized data - WBS Level

1 reply [Last post]
Haresh Jayanth
User offline. Last seen 6 years 25 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219
Hi,

If we input at project tab - summarized data to WBS level, and if then summarize at level 2, 3 , or 4 , primavera doesnt summarize the project, what is the use of this function, if no changes is happening on the project level??

regards,


Haresh Jayanth

Replies

Rodel Marasigan
User offline. Last seen 11 weeks 21 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Haresh,
I already answer this to you before; Summarized data to WBS level is for tracking module. It will expand/collapse all projects up to 2 level only if projects are closed and data are being updated when Tools->summarize is run.