S CURVE BY ACTIVITY PROFILE- urgent question

2 replies [Last post]
Alaa Al haj
User offline. Last seen 7 years 24 weeks ago. Offline
Joined: 7 Nov 2007
Posts: 79

Hi
can i use activity profile usage or resource usage profile to produce manpower histogram and s curve progress
keep in mind that each activity has resources ( trade & quantity) like carpenter 10 Hours, steel fixer 15 Hours ... etc

Regards
alaa Al Haj

Replies

Alaa Al haj
User offline. Last seen 7 years 24 weeks ago. Offline
Joined: 7 Nov 2007
Posts: 79
Thanks arnold

you save me


Arnold Puy
User offline. Last seen 9 years 25 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

Yes.