Splitting / Necking in P6

3 replies [Last post]
Athar Hashmi
User offline. Last seen 3 years 45 weeks ago. Offline
Joined: 21 Mar 2009
Posts: 38
Dear Freinds

Please help me to show the necking in bars in P6. How can I show splitted activity. I already marked check boxes ’calendar non-working time/activity non work intervals’, but necking is not appearing in bars.

Replies

Neal Walsh
User offline. Last seen 3 years 40 weeks ago. Offline
Joined: 16 Sep 2007
Posts: 49
No probs Athar, glad you have it sorted now ;)

Walshy
Athar Hashmi
User offline. Last seen 3 years 45 weeks ago. Offline
Joined: 21 Mar 2009
Posts: 38
Thanx Neil, it’s working now.
(I wasn’t doing this (necking) for every bar.)
Neal Walsh
User offline. Last seen 3 years 40 weeks ago. Offline
Joined: 16 Sep 2007
Posts: 49
Athar,

By splitting, do you mean you want to stop an Activity on a certain date then commence at a later date? Or do you purely just want to ’neck’ or sausage the bars as I call em?
By right clicking the Gantt Chart / Bars / Bar Settings and then by checking the calendar non-work time box ( dont forget you have to do this for every bar you want to be necked) then this should work.....

Walshy