Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P6.2 : Planning unit

9 replies [Last post]
Khuong Do
User offline. Last seen 15 years 33 weeks ago. Offline
Joined: 22 May 2009
Posts: 27
Groups: None
Hi.
I plan for a resource assignment like this : Jan (1000 hours) Feb (1000 hours) Mar (1000 hours).
On Jan I used only 800 hours. Primavera will spread the remaining hours (2200) evenly to Feb and Mar.
Can Primavera put remaining 200 hours from Jan to Feb (remaining unit of Feb will become 1200), not spread out to remaining duration like what it does now.

Thanks & regards
Khuong

Replies

Rafael Davila
User offline. Last seen 3 weeks 2 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241
Use the Resource Assignments Worksheet.

resource assigments 2
Khuong Do
User offline. Last seen 15 years 33 weeks ago. Offline
Joined: 22 May 2009
Posts: 27
Groups: None
Hi.
I checked but there is not any resourve curve which solve my situation.
Rafael Davila
User offline. Last seen 3 weeks 2 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241
If some of your activities require unique future period allocations because planned work cannot be accurately distributed using custom resource curves, you can manually enter future period budgeted and remaining units values for assignments in the Resource Usage Spreadsheet (Resource Assignments and Activities windows).
Nestor Principe
User offline. Last seen 13 years 39 weeks ago. Offline
Joined: 23 Oct 2008
Posts: 151
Would the resource curve can do the trick?
Brad Lord
User offline. Last seen 10 years 40 weeks ago. Offline
Joined: 27 May 2003
Posts: 256
Groups: None
You can insert the remaining resource as a remaining start as you can with in progress activities, or assign the resource multiple times and change the planned start date
Andrew Podolny
User offline. Last seen 1 year 35 weeks ago. Offline
Joined: 16 Nov 2004
Posts: 130
Hi Khuong,
You can use ’Future period bucket planning’ in P6 to manually allocate resource units for each month. But this proccess isn’t automated and every time you update your schedule - you have to review the future buckets values and they (based on my experience) are very sensitive peace of data just check the related section in P6 Help. So theoretically you have ability to control resources distribution the way you want but it’s very hard in practice. I gave up doing this on weekly basis.

Regards,
Andrew
Dieter Wambach
User offline. Last seen 7 years 46 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Khuong

I don’t know any P6 function to provide this. Maybe someone else has an idea.

Regards
Dieter
Khuong Do
User offline. Last seen 15 years 33 weeks ago. Offline
Joined: 22 May 2009
Posts: 27
Groups: None
Can we make the process automatically? Something like if we do not use all budget unit of this month, the rest will be brought to next month only, not spread evenly to remaining duration. The same process will be repeated for next month.
Now we have to reassign it manually.

Regards
Dieter Wambach
User offline. Last seen 7 years 46 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Khuong

You can do this with the web module. With the normal P6 you’ll need two assignments.

Regards
Dieter