What is Remaining Float?

D
David Kelly 👤 Member for 21 years 8 months

Since remaining float is based on the remaining early start, it will be different from total float if the project has been resource leveled.

A
Anoon Iimos 👤 Member for 19 years 9 months

here are my guesses:



1. Remaining Float = Total Float (for all Baseline / Target Schedules - which are not updated or progressed ever)



2. Total Float(s) changes once the schedule is updated or progressed not exactly as planned. Once activity or task is completed, its total float becomes zero.



3. Therefore, Remaining Float(s) is a variable figure that goes with the updates, and mathematically the same as Total Float(s).


Forum Sponsor

Top Posters

AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts