importing activities from excel

1 reply [Last post]
james maccammond
User offline. Last seen 13 years 16 weeks ago. Offline
Joined: 19 Nov 2007
Posts: 3
why does the import put my imported activities at the bottom of my project? Even after I have assigned an Activity ID.

Replies

Arnold Puy
User offline. Last seen 9 years 32 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
James,

Perhaps, it is because you did not assign Activity Codes or define WBS in your Activities. Try to do this in excel or by using Global Change or even by dragging your activities to their respective groups.


Arnold