Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

IMPORT P3 PROJECT TO P6 IS PAIN....BIG ISSUE

3 replies [Last post]
Suresh Sankaranku...
User offline. Last seen 5 years 21 weeks ago. Offline
Joined: 30 Jul 2006
Posts: 77
HI Dear Friends,
I am facing a big problem of importing the p3 (project planner 3.1) project to p6 6.1 version. The problem is the original budgeted units are getting huge difference in p6.
I tried to import a proj into p6 from p3. In p3 the budgeted unit was 90hrs and but when i imported it into p6 its give 800hours... I been ......f....d in the meeting ...I just thought p6 is reliable and wont make me wrong..............

Pls if you have any clue pls share....
Thx
Suresh

Replies

Dieter Wambach
User offline. Last seen 7 years 37 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Suresh
If you walk through the import you see a window "Update Project Options". Select "Advanced" in the bottom of this window. Then try "units as hours".
Sorry, one of your sentences I don’t understand: "... in p3 is 4 duration is 10 days". What do you mean by this 4 = 10 ???
Regards
Dieter
Suresh Sankaranku...
User offline. Last seen 5 years 21 weeks ago. Offline
Joined: 30 Jul 2006
Posts: 77
Diater,
The units are same in p3 and p6. What i found is.. Unit per time in p3 is getting wrongly calculated in the p6

Eg: 8hrs per day calender
unit per day is specified in p3 is 4 duration is 10 days

In p6 it converts like this

4*10=40*8 = 800h i dont knnow how its come.. but i think this is the funda... bullshit p6..

Cheers



Dieter Wambach
User offline. Last seen 7 years 37 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Suresh
Just two ideas:
1. Parameter Planning Units: Hours or Days: May be you selected days but planned in hours.
2. Resource curves: Sometimes not really compatible - e.g. "curve A" bell shaped in P3, triangle in P6.
May be others have more ideas.
Regards
Dieter