showing relationships

3 replies [Last post]
prem kumar,
User offline. Last seen 13 years 10 weeks ago. Offline
Joined: 9 Mar 2005
Posts: 14
Groups: GPC Qatar
hi

When you show, target and current bars in gant chart view, how to show the releation ships line between the current bars. mine is showing the relationship for the target bar

regards

prem

Replies

James Shimmon
User offline. Last seen 13 years 51 weeks ago. Offline
Joined: 12 Jan 2007
Posts: 93
no, it is just something I found out when I was experimenting because I had the same problem
prem kumar,
User offline. Last seen 13 years 10 weeks ago. Offline
Joined: 9 Mar 2005
Posts: 14
Groups: GPC Qatar
Thank you very much.

where did u get it, is there in the primavera manual?

regards

prem
James Shimmon
User offline. Last seen 13 years 51 weeks ago. Offline
Joined: 12 Jan 2007
Posts: 93
right click in the gantt chart view and shift the Primary baseline bar and primary milestones down to the bootom of the list,should sort it out. Quirk of the system!!!