Jiayin Yao
User offline. Last seen 13 years 33 weeks ago. Offline
Joined: 23 Mar 2007
Posts: 15
Groups: None
Hello all,

I am graduate planner , had quite short working experience with P3e . I am trying to work out the budget manhours by report wizard . I can work out the monthly budget manhours . But follow the same steps to work out the weekly one. The date interval changed in to week , but the budget manhours is still monthly . Can anyone tell me how to work out the budget manhours by week please .Thank you very much .

Regards

Jia

Replies

Jiayin Yao
User offline. Last seen 13 years 33 weeks ago. Offline
Joined: 23 Mar 2007
Posts: 15
Groups: None
Sorry , Wrong face....
Jiayin Yao
User offline. Last seen 13 years 33 weeks ago. Offline
Joined: 23 Mar 2007
Posts: 15
Groups: None
Hi Dieter ,

Thank you very much for your help . It works now .

Regards

Jia yin
Dieter Wambach
User offline. Last seen 7 years 27 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Jia
I’m not sure if I really got your question.
Have a look under Edit --> User Preferences --> resource analysis. The last line is "Interval for resource calculations". There you entered "Month", I suppose. Then the smallest intervall for calculations will be the month. Change it into days or week - depends on your reporting needs.
Hope, this will help.