P5 for shutdown planning

3 replies [Last post]
ALKA REVO
User offline. Last seen 11 years 20 weeks ago. Offline
Joined: 23 May 2007
Posts: 20
Is anybody using P5 for shutdown planning? I have used fixed duration and units as duration type. Does that sound alright. I am using P5 without any formal training. Since I have worked on P3 for many years, I have worked out most of P5 but still there is a lot to explore.

Replies

David Kelly
User offline. Last seen 2 years 8 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
All,

the way I help clients chose which duration type to use is to tell them that each activity has THREE dimensions:

Duration
Number of men
Total Manhours (duration x Number of men)

If you ask an engineer how "big" a job is, do they tell you:

Its a three day job
Its a two man job
Its a 50 manhour job

By ranking the above list, and comparing it to the order that each of those variables is recalculated by the four duration types, you should be able to work out which is best.

I am blessed with clients who scope the work for Shutdowns/Turnarounds very well. So in that world its a "50 manhour job" - so we use "Fixed duration and units"

Marcio Sampaio
User offline. Last seen 12 years 4 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
I used same during a HOT STRIP MILL Repair.

Regards.
Dieter Wambach
User offline. Last seen 7 years 23 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Alka

We used it for shutdown planning.
Fixed duration and units seems the best choice.
You plan with fixed durations --> no surprises with the overall duration
Fixed Units: better for the planned resource load and by this for simulations.

Good luck

Dieter