P3e basics

2 replies [Last post]
mh shaw
User offline. Last seen 16 years 3 days ago. Offline
Joined: 8 May 2007
Posts: 22
when i was making relationship and i was making predecessor and successor, my activity sequence was changed. How can I get back the sequence ?

Replies

Marcio Sampaio
User offline. Last seen 12 years 4 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Go on group & sort / sort by ... or just click on header column.

Regards.
Rodel Marasigan
User offline. Last seen 17 weeks 2 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
mh shaw,

If your activity sequence is by activity ID just click the headers of activity ID and it will sort by activity Id or click any headers that correspond to your original sequence such as start, finish...etc

If you’re not happy on the result, use group & sort to organise your activities.

Hope this help.