Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Importing P3 projects - activity codes

4 replies [Last post]
Neal Carter
User offline. Last seen 12 years 40 weeks ago. Offline
Joined: 7 Nov 2006
Posts: 3
Groups: None
Hi everyone.

We are doing a lot of migration of projects from P3 to P5 and are concerned that the activity codes are made global automatically. Is there any way that we can ensure that the codes are either EPS or Project codes?

Thanks

Neal

Replies

Chris Radecki
User offline. Last seen 7 years 21 weeks ago. Offline
Joined: 11 May 2005
Posts: 35
On the question, a RAG way be to use xerFileParser&Builder.xls from P3 POINT site.

Setup projects with activity codes and dummy activity codes value, export them to xer, use the above xls to split the activity codes

Cannot remember how to export activity codes from P3, but sure there is a way.

Copy to the xerFileParser&Builder.xls and convert to xer and import.

Sorry that it is RAG.





Chris Radecki
User offline. Last seen 7 years 21 weeks ago. Offline
Joined: 11 May 2005
Posts: 35
Take care with activity codes at EPS or Project level. I am not too cluey on importing them, but....

There is a glitch with Puge Deletes in 5sp1/0 where EPS or Project level activity codes can bedeleted from the activity ID assignation.

I like the codes at EPS/Project level - just have to accept that have to export/backup the acivity assignation, and reimport when they are lost.

Maybe SP2 solves this problem; not using purge deletes seems also to work at present ;-)
Sufian Malik
User offline. Last seen 17 years 35 weeks ago. Offline
Joined: 24 Nov 2006
Posts: 15
Groups: None
Additonal information:

When going through the import :

1)If you select ’combine sub projects’ then the project codes are added in the activity codes dictionary at a project level

2)If you select ’create separate projects’ then they should be added at a global level.
Sufian Malik
User offline. Last seen 17 years 35 weeks ago. Offline
Joined: 24 Nov 2006
Posts: 15
Groups: None
Hi there

When importing a project, activity codes are added in the project dictionary of activity codes

Regards

Sufian