Resource progress (v.5.0).

3 replies [Last post]
Marcio Sampaio
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Dear all,

I heard that when u give progress to activities - on V.5 - resources are not automatically progressing.

Dp u know something about it?

Regards.

Marcio Eduardo.

Replies

Marcio Sampaio
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Rajeev,

The option is select. But resources are still not automatically progressing.

I’m afraid it’s something new on V.5 (or a bug). Better return to P3e v.4.1

Regards.

Marcio Eduardo.
Marcio Sampaio
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Ok.

I’ll try it and return to u results.

Regards.

Marcio Eduardo
Rajeev Nelliyodan
User offline. Last seen 8 years 24 weeks ago. Offline
Joined: 21 Feb 2002
Posts: 28
Groups: None
Try clicking on "Recalculate Actual Units and Cost when duration % complete changes" under calculation tab in Project view.