Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Peak Usage for Resource Loading in P3e/c

2 replies [Last post]
Vamsi Kolliboina
User offline. Last seen 1 year 7 weeks ago. Offline
Joined: 3 Sep 2001
Posts: 15
Groups: None
Hi All, I used take the Peak Usage of Resources from the Resource Loading Report. I am unable to do the same with P3e/c anymore. I hope they add this functionality in their next release. In the mean time is there any easy workaround ? Cheers, Vamsi

Replies

Vamsi Kolliboina
User offline. Last seen 1 year 7 weeks ago. Offline
Joined: 3 Sep 2001
Posts: 15
Groups: None
Alex,

Yeah,I am importing the data into excel right now.But its bit tedious when u have to do a Weekly Peaks report for a project with duration of 24 months. I hope primavera will add this feature in the ver.5(I have pointed out this to them,anyway)

cheers,
vamsi
Alex Wong
User offline. Last seen 11 years 36 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Vamis

One work around is to use resource table by date
Export the table to Excel run a function to select the max from each week/month/quater.

That should give u a table with peak resource usage @ the time period you wanted

Cheers

Alex