Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

on tracking

4 replies [Last post]
Francis Moyalan, ...
User offline. Last seen 5 years 28 weeks ago. Offline
Joined: 12 Feb 2005
Posts: 105
Groups: None
hi,
can any body help by explaining me how to do the tracking in a project....

along with that can any one help me by telling the new versions of primavera and it’s various applications...

Replies

Anand Kulkarni
User offline. Last seen 12 years 20 weeks ago. Offline
Joined: 4 Apr 2005
Posts: 41
Groups: None
Few more...

Schedules are mainly tracked on three things

1)Time
2)Resources i.e. Man, Material,Money
3)Site Inspection

The presentation of the these parameters can be done in many forms depending on the level at which are to be presented.

Dayanidhi Dhandapany
User offline. Last seen 3 years 35 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
Tracking:

1. Establish baseline programme.
2. Distribute monitoring sheets to relevant supervisors(capture the relevant information you need to update schedule)
3. Set up the periodical updating date before which u need to receive the item 2.
4. Update the schedule(use baseline your target to check for any slippages)

in the next update, use the prev. update as your one of target schedule to verify any activities slipped from the completion dates, check over all project completion date...

many more things to add............


Sukumaran Subaram...
User offline. Last seen 9 years 19 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
Hi,

What do you mean by HOW TO DO THE TRACKING IN A PROJECT?
Is it MS Project schedule or P3e schedule.

Regards.