Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Very high Values in Actual Cost!!!

1 reply [Last post]
Adam Salam
User offline. Last seen 8 years 13 weeks ago. Offline
Joined: 13 Jul 2016
Posts: 3
Groups: None

Hi Everybody :)

I am using Primavera P6 rel 8.4 to exeperince some scinarios in constuction projects

after partial planning and trying to enter Actual units for cost/time control

I found the the resultant Actual cost very high?

see the screenshot

 

 

what could be the problem?

thank you for sharing your knowledge :)

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

wrong forum 

go to project higlight your project go to the calculations tab

under resource assignments make sure that subtract actual from at completion is checked NOT ADD actual to remaining