UPDATE PROGRESS MANUALLY

4 replies [Last post]
vex zex
User offline. Last seen 14 years 3 weeks ago. Offline
Joined: 7 Jul 2010
Posts: 42
HYE ALL

i WANT TO ASK SOMNTHNG ABOUT UPDATING SCHEDULE...
hOW TO UPDATE MANUALLY AND NOT EFFECTED THE EARLIEST START DATE FOR THE REMAINING ACTIVITIES...

THANKS

Replies

vex zex
User offline. Last seen 14 years 3 weeks ago. Offline
Joined: 7 Jul 2010
Posts: 42
thanx fren
Rodel Marasigan
User offline. Last seen 4 days 21 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Vex,
Update % complete and enter remaining duration. Do the same on resources if assigned. Very simple.
vex zex
User offline. Last seen 14 years 3 weeks ago. Offline
Joined: 7 Jul 2010
Posts: 42
hye anoon

thanks for the suggestion..
how to update the progress each activity if not based on duration and just based on pysical percentage
Anoon Iimos
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Vex,

That is not possible if your activities are not progressing as planned. However, it maybe done by reducing some durations for your activities, or why not use your baseline or target (progressed as planned)?