Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

"0" Month

1 reply [Last post]
Angel Cruz
User offline. Last seen 11 years 34 weeks ago. Offline
Joined: 16 May 2010
Posts: 16
In overall appearance of P3 on the time scale. Considering the "Months" it shows for example -1 and then 1. My question is can we include "0" Months in between?

Replies

Rodel Marasigan
User offline. Last seen 1 week 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Angel,
The answer is "NO" because there is no month in between.
Example of ordinal dates:
If Project Start Date = Jul 2010 and Ordinal date set at Sep 2010 then:
-2 Jul
-1 Aug
1 Sep etc..