Calendar problem message

2 replies [Last post]
stephen hobbs
User offline. Last seen 1 year 39 weeks ago. Offline
Joined: 21 Aug 2006
Posts: 8
I am getting a calendar problem message each time i schedule the project. When I look at the scheduling report I find this text

"Calendar problem detected, you should move the calendar start date earlier and re-schedule.
(Could also be caused by Constraint Dates or Imposed Finish Date off the calendar.)"

I am struggling to find what the problem is exactly - anyone with any ideas?

Replies

Dieter Wambach
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Stephen

Check the Clendar start dat under
Data --> select "Global" --> Standard --> Calendar Start

Regards

Dieter
Alex Wong
User offline. Last seen 11 years 35 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Hi

Is this a P3 or P6 problem??

I suggest you check with any activities have any "Must finish Contraint

HTH

Regards

Alex