can I put RD > OD in P3 !

5 replies [Last post]
mimoune djouallah
User offline. Last seen 5 years 31 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388
hi dear planners

when i update my program, i have some activities which has RD > OD( updated manually), but i can’t get P3 to show me the total percent complete of the project, it show always zero.

any idea ?

mimoune

Replies

mimoune djouallah
User offline. Last seen 5 years 31 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388
thanks really
mimoune djouallah
User offline. Last seen 5 years 31 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388
escander yeah my friend, i am always in arzew, now it become very interesting, many nationalities, we lack only people from Antarctica.

Joao Reibero, yes of course, this option is off, otherwise i can’t get P3 to show me, RD> OD

Please can you take a look at this thread and tell me what you think !!

http://www.planningplanet.com/forum/forum_post.asp?fid=&Cat=1&Top=58911&...

thanks very much
Joao Ribeiro
User offline. Last seen 6 years 25 weeks ago. Offline
Joined: 21 Mar 2003
Posts: 64
Have you checked the options "Link remainig duration and schedule percent complete" and the ones for summarization?

HTH