No Subject Specified

2 replies [Last post]
Ernani Garena
User offline. Last seen 12 years 48 weeks ago. Offline
Joined: 4 Dec 2008
Posts: 36
I would like to seek for assistance. I have created a schedule but my boss ask me to prepare a one-month ahead schedule from the original schedule I have created to be provided to subcontractors. My problem is I have tried to do it using global change but everytime I press F9 it returns to original schedule I have created not making it one-month ahead. I have also tried to change the start date from project overview but nothing happens. The schedule have some constraint dates. Thank you very much!

Replies

Ernani Garena
User offline. Last seen 12 years 48 weeks ago. Offline
Joined: 4 Dec 2008
Posts: 36
Alexandre,

Thank you very much for your response, I have done your second suggestion & it works! If possible because I am not yet very familiar using global change, can you send me a tutorial or some useful information with global change. My email address is ernan0518@gmail.com

Thank you very much!

Regards,
Ernani