How to make a sub-project?

10 replies [Last post]
John Pahanonot
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 17 Jul 2006
Posts: 13
Hi guys i need to know how to create a sub project.

Replies

John Pahanonot
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 17 Jul 2006
Posts: 13
Hi Guys,
thanks for the information. i really solve my problem already by reading some samples and trying make my own and i found out what i am going to do.

regards
John Cornish
User offline. Last seen 10 years 49 weeks ago. Offline
Joined: 22 Nov 2007
Posts: 49
Hi,
Micro Planner X-Pert offers up to 100 sub-projects each having their own logic diagram and critical paths. And all drawing from the same pool of resources. It could not be easier.
Tommy Nug
User offline. Last seen 6 years 8 weeks ago. Offline
Joined: 16 Nov 2007
Posts: 44
I also found that P6 is much easier for us to make sub-project and WBS as well.

Cheers,
Tom
Ahmed Khan
User offline. Last seen 15 years 42 weeks ago. Offline
Joined: 3 Dec 2008
Posts: 29
Alexandre,

In P3 it will be very difficult to prepare a sub project. If it would been P6 i would solved Ur problem.

Regards

Maask
Ahmed Khan
User offline. Last seen 15 years 42 weeks ago. Offline
Joined: 3 Dec 2008
Posts: 29
Hi

Could U Plz tell me which version of primaveera U r using..?

Regards

Maask
John Pahanonot
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 17 Jul 2006
Posts: 13
i didt it already but the activity is not showing. is there other way to created that?
Tommy Nug
User offline. Last seen 6 years 8 weeks ago. Offline
Joined: 16 Nov 2007
Posts: 44
hi,
I am not sure that any topics in this forum mention about this or not, but still show you an idea for that:
You create a master project first, then create sub projects later in the same group name.
To do that, Mount to File/ New, and tick to "Add this new project to a project group", choose the Master schedule and remember to type the sub-project name.

Hope this helpful.