Primavera P5

1 reply [Last post]
J Venkatesh PMP P...
User offline. Last seen 11 years 29 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 52
Groups: GPC Qatar
Friends,

Am familiar with P3 and new to P5...

Can any one guide me the step by step instructions to do the following in P5..

1. Add base line to a Project in P5..
2. Prepare a layout showing the coomparison bars of two or three projects..
3. How to use import and export files from Excel..(In P3 I used to export the files to Excel and enter the resource units or somethig in Excel and import it back to P5..Can I do the same thing P5)

Advance thanks my frnds...

Jaya

Replies

Arend Kok
User offline. Last seen 10 years 48 weeks ago. Offline
Joined: 19 May 2008
Posts: 38
Hi Jaya.

You can use the maintain baselines under your project menu to create baselines. Keep in mind that if you create a baseline from a project that project will be removed from the projects list. You can the assign baselines to a project and select the bars if you right click the bars option on your gant chart.

The help file also contains alot of information on exporting to and importing from excel.

Hope this helps.