janice hillenmeyer
User offline. Last seen 15 years 2 weeks ago. Offline
Joined: 30 Oct 2008
Posts: 5
So in P3 you had the option of when scheduling to select Options and under Schedule Durations you could select Contiguous (default) or Interruptible. Is this same option available in P6? If so, how do I select it?

Replies

Dieter Wambach
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Janice
This option does not exist in P6.
Dieter