VO & Working Programme

No replies
Sajid Balma
User offline. Last seen 13 years 35 weeks ago. Offline
Joined: 8 Jun 2007
Posts: 151
Groups: None
Dears
I have a situation here. After completing more than 50% of civil works, the Engineer issued a VO slashing the whole of the civil works from our scope.
Now, I was asked to resubmit working programme based on this VO.
My question is what would be the best way of reflecting this VO in my programme. Should I go with dissolve activities? Should I need to update the baseline also?

Please enlighten me.