Constarints in Primavera

1 reply [Last post]
Daniel Situmorang
User offline. Last seen 14 years 2 weeks ago. Offline
Joined: 3 Sep 2003
Posts: 9
Groups: None
Hi all,
When applying contraints to a particular type of activity, are there any exclusions? I’ve recently imported a contractor’s schedule and experienced that a particular date (finish milestone) that has been given a ’finish on or before’ constraint, moved.
Appreciate any insights.
Thansk.

dts

Replies

James Braghini
User offline. Last seen 14 years 7 weeks ago. Offline
Joined: 28 Apr 2008
Posts: 51
Groups: None
I would not use any contraint on the finish milestone. I would have the drop dead completion date placed in the Project Data.

Good luck on you project.

James B.