Recovery Schedule

1 reply [Last post]
Ashutosh Nema, PMP
User offline. Last seen 12 years 41 weeks ago. Offline
Joined: 24 May 2008
Posts: 40
Groups: None
Any body is having idea abot recovery schedule.

Ashutosh Nema

Replies

Dionesio Cornico
User offline. Last seen 14 years 1 week ago. Offline
Joined: 11 Oct 2007
Posts: 7
If the Project Completion or Contractual Milestone(s) is/are probably to be delayed and then your client wants you to complete the said schedule maintaining the contractual "Project Completion" or "Milestones".