Resource updating

1 reply [Last post]
Christian Adrian ...
User offline. Last seen 5 years 30 weeks ago. Offline
Joined: 3 Jun 2003
Posts: 193
Groups: None
Dear All

I have problem regarding resource updates and seek and an advise from you guys, the case is like this: everytime I do a weekly progress update in P3 and then export the resource loading into excel a negative values always occur. I’ve checked the P3 file and it seems that it’s been automatically updating the actual this period quantities with negative values even though the task hasn’t progressed yet. I’ve done a check on the task constraint and automatic cost/resource calculation rules, no constraint and there was no check on the link to duration & sched. %, freeze resource units per time perion, which I think should fine..

Has anyone ever encountered the same problem, or have I missed some steps in the checking procress? Please help..

Replies

Ameen Pasha
User offline. Last seen 11 years 2 weeks ago. Offline
Joined: 16 Jun 2008
Posts: 21
please help me out with the same regards....



with regards,

Mr. Ameen n Pasha,
ameen_pasha10@yahoo.com