Earned Value and Duration % Complete

1 reply [Last post]
Dean Mulligan
User offline. Last seen 6 years 10 weeks ago. Offline
Joined: 7 Mar 2007
Posts: 7
Groups: None
on my project the guys are trying to get the programme cost loaded to meet the clients requirements regarding EV. And are having trouble, mostly due to a disconnect between the cost breakdown and the WBS - costs are at a high level only - thats their problem!

What my problem is that the % Complete used is Duration % Complete.

I have only used Physical % Complete before for EV analysis, is it possible to use Duration % Complete ????

Does Primavera V5 calculate it and does it roll up properly???


cheers

deano

Replies

David Kelly
User offline. Last seen 2 years 29 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
There is no distinction between using either Physical % or Duration % complete in order to set Performance % complete (which is how P5 calculates Earned Value)

Duration % complete DOES roll up "properly" - but I cannot imagine what you would use that for if the client understands EVA - why not just roll up Performance % complete?