Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Cost resource loading & Cash flow

4 replies [Last post]
ananda vijayan
User offline. Last seen 13 years 27 weeks ago. Offline
Joined: 29 Apr 2008
Posts: 16
Friends,

I am using P3 for planning and scheduling. I have used the man-hours basis doing all the work. Now first time i want to use the cost resources like labour cost, material cost, equipment cost, subcontract cost and sundry cost for all activities (direct & indirect costs) and i want to create a cash flow from P3. How can i assign all activities the above costs? Anybody help in the above matter or please give an short notes for that?

Thanks & Regards,

VJ

Replies

Rafael Davila
User offline. Last seen 2 weeks 4 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241
If you want to record true historic cash flow remember to use Store Period Performance command (Tools menu) from the very beginning of your job.

Normally P3 spreads actual data evenly from the recorded actual start date to the data date. However, you can use this dialog box to have P3 store actual cost, use, and earned value for each update period. As the project moves forward, you can analyze historical data using the Resource Table or Resource Loading report. P3 displays the previous closeout date, and sets the new closeout date equal to the data date in the dialog box.

Do you want to model true job costs as an expense and Payment Berakdown as in income? What about lag between execution and chash movement? I believe for Cash Flow you need both, income and expenses. Are you going to expose confidential cost data to others that will have access to your schedule?

Well you can generate nice S curves with P3 altough as unreliable as the ones you can generate using Excel alone. The good thing about Excel curves is that they will be as unreliable but better looking.

Best regards,
Rafael
Abu Lana
User offline. Last seen 5 years 8 weeks ago. Offline
Joined: 17 May 2008
Posts: 24
Groups: None
Upload percentage on activities.

you can sort your percentage rates from priced BOQ where you can distribute the total percentage of a trade into its breakdown over the different sectors, floors, ...
then assign cost/unit = 1 in cost (rosources window) automaticly it will be assigned as cost.

in a project you don’t need to interfer into diffrent costs of labor and equip.* assign it as per BOQ and it will result a 98% accurate Cash Flow.

Take care.
Mujahid Akhtar
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 19 Apr 2007
Posts: 30
Use the Cost form or the activity columns in the Bar chart view to assign cost data to each activity.

1. To open the Cost form, do one of the following: Select an activity, click the right mouse button, and choose Activity Detail, Cost.Double-click an activity and click in the Activity form.Select an activity and press Ctrl+T.

2. To update activity costs or resource quantities, click the appropriate resource column in the form; then enter the new value and click .

If you define unit prices for resources in the Resource Dictionary, P3 automatically recalculates cost estimates based on the quantities entered in the Resources form.
Johny Kesserwany
User offline. Last seen 7 years 45 weeks ago. Offline
Joined: 18 Sep 2007
Posts: 118
the same way as Resouces:
You define all resources
you choose global change for fast assign to all resources
You assign the respectives costs in COST by activity

NB: assign cost accounts it will help later in the cost management

for the cash flow report: Tabular or Graphic for Cost and you’ll choose for which resource or for the total cost you’ll leave the resource selection blank

good luck