P6 TO P3

13 replies [Last post]
Emre Bayrak
User offline. Last seen 9 years 35 weeks ago. Offline
Joined: 23 Apr 2003
Posts: 18
Groups: GPC Qatar
Hi All

I have to continue submitting my files using P3.1 according to my contract. If I purchase P5 or P6 and use, will it be efficient to convert P6 file to P3 format when it is required?


Best Regards

Emre

Replies

Justin James
User offline. Last seen 5 years 38 weeks ago. Offline
Joined: 19 Aug 2009
Posts: 32
Groups: GPC Qatar, TILOS

Hello everyone,

Can anyone tell me , how to convert a project from P5 to P3..step by step explanation will be helpful

Regards

Justin,

Qatar

AKSHAY KAWADE
User offline. Last seen 9 years 5 weeks ago. Offline
Joined: 10 Oct 2010
Posts: 3

I HAVE CONVERTED PROGRAMME FROM P6.1 TO P3.

DURATION IN P6 & P3 FILE IS NOT MATCHING EVEN START & FINISH DATES ARE MATCHING

PLEASE HELP ME OUT.

 

 

THANKS IN ADVANCE

AKSHAY..

Anoon Iimos
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
P6 to P3? you might encounter problems exporting WBS
Dieter Wambach
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Emre

If you create a project for a contractor who won’t use P6, export --> contractor will update --> import with the option "update existing project", it should work if both sides are aware of the differences.
But another idea: It seems a bigger project with some budget. Why not grant the subcontractor access to your database? As version 6 MyPrimavera is usable. With a good security concept the contractor has no chance to get to other data and only your admin will be able to read all his data. It’s a question of confidence of course.
I don’t really like if different software is used.
Regards
Dieter
Emre Bayrak
User offline. Last seen 9 years 35 weeks ago. Offline
Joined: 23 Apr 2003
Posts: 18
Groups: GPC Qatar
Dear All

Thanks for all answers, let me give more clarification,

My project will a long term one, i am sure i need to coordinate many subcontractors that will use P6 , on the other hand I also believe it will be much more efficient for me to use P6 for my team work also.

Assuming a user is aware of P3 limitations and respecting them while using P6, Is it only a command to transfer from P6 to P3 or it is combination of various actions and modifications such we face transfering from MSproject to P3?

Best Regards
Dieter Wambach
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi

An addition: If you have to cooperate with a partner, both must use the same software with the same release state. It is reported, that one of the major problems, Airbus Industries had with the A380 was due to develop different parts with the same software, but different release states. Later, when they had to cooperate, it didn’t work --> redevelopment required.
Cheers
Dieter
Dieter Wambach
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Benjamin
For contractual reasons only.
Dieter
Benjamin Mora
User offline. Last seen 11 years 18 weeks ago. Offline
Joined: 19 Oct 2007
Posts: 66
Groups: None
I would go to P6 in a heart beat, if there were no conversion issues.

But if I follow your logic: why would you, from your professional experience, convert the file ever? You said yourself that the planning\scheduling should be done in one package.

I was not endorsing one strategy over another.
Dieter Wambach
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Benjamin
It depends from which information you want to transfer, if reliable or not.
A change to P6 very soon will lead you to take advantage of the additional features. Most companies nowadays want to have an overall reporting, an overall resource-planning etc. So it will depend on your strategy, which software to use - or which combination. Planning and scheduling must be done in one package only. Never do planning in parallel!
It’s difficult, but if you’ll regard P3-related restrictions, I found the export reliable for all basics. But it is a break of structures. In German, we call interfaces by the translation of "cuts" - they always hurt.
If planning is required by contract for a certain package, follow the contract; if just a monthly data-file is required, do the planning in your mainline package and export the monthly file.
My own opinion!
Regards
Dieter
Benjamin Mora
User offline. Last seen 11 years 18 weeks ago. Offline
Joined: 19 Oct 2007
Posts: 66
Groups: None
We are going through the same thing with my company with the Army COE. I have been told by a company in Dallas, IMS, that has exclusive rights in Texas to deal Primavera that the backwards conversion from P5\P6 to P3.1 is not reliable. You have a couple of choices once you migrate to P5\P6:

1) Use the converted schedule and correct the conversion errors.
2) Use P3.1 to create the schedule, while maintaining both systems in parallel. There are obvious tradeoffs.
3) Try to talk the "owners" into converting to P5\P6. This migration is inevitable, in my opinion.

This all depends on your client. The Army COE does not make software decisions over night. However, if your client is the COE, I have never found languange in a contract the compels the contractor to use P3.1. In fact, the whole rationale behind using the SDEF file format was to allow their contractor’s to use alternate software, even though P3.1 has been tested to produce a reliabel SDEF compliant data dump.
Bijaya Bajracharya
User offline. Last seen 8 years 31 weeks ago. Offline
Joined: 25 Feb 2005
Posts: 175
Groups: None
Please ignore the incomplete last paragraph in my last posting.
Bijaya Bajracharya
User offline. Last seen 8 years 31 weeks ago. Offline
Joined: 25 Feb 2005
Posts: 175
Groups: None
Emre,

You said "I have to continue submitting my files using P3.1 according to my contract. If I purchase P5 or P6 and use, will it be efficient to convert P6 file to P3 format when it is required?". And the simplest answer with the information you provided is NO.

If you have to submit your files in one software, why one earth do you want to use another software? This not an upgrade. This is completely new software. As between any two software, all features of one is not supported by the other. Though P3 3.1 and P5/P6 come from the same company, they are different software (not really upgrade).

Three conditions I will start using P5/P6 or any other software for a contract which needs submission in P3, if I were in you place are:
1. My P3 licence is being revoked and replaced by P5 or P6.
1. All my other programmes have to be planned in that new software.
2. For the existing contract where programme have to be submitted in P3 foramt, I do not need to import the project back to P5/P6.





If you only have to submit
And the other thing is that the moment you start using P5 or P6, it is just natural that you start using its features (which are not supported in P3) only to be disappointed that exp
Dieter Wambach
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Emre
There are many reasons to change to Primavera Enterprise.
We use P6 as a mainline but still have old p3 licenses for cases as yours.
My opinion: Use P3 for this project it is an excellent tool as well.
The export from P6 to P3 3.1 will work reliable if you’ll regard P3’s restrictions for a project planned and controlled in P6:
- Id-lengths and restrictions
- Only use one hierarchy level
- no roles
....

Have a look into the pdf on the P6 documentation cd: Moving from P3 to P6 (or P5) - a good overview on the differences.

Good luck for your project!