Prioritising the Activities!

1 reply [Last post]
Siva Kumar
User offline. Last seen 6 years 4 weeks ago. Offline
Joined: 5 Jul 2005
Posts: 44
Groups: None
Hello all,

This is regarding summarising the actitives..
In a project schedule,let us consider an operation,which consists of some 5 activities,out of that, 3 activies are the main work,90% complete.And other 2 activities,which is say,final cleaning up works,which is 0% complete.

So,when u summarise the operation it will take an average of 55%.This makes an embarassing report about that operation.

Can anyone say whether the less important works can be prioritised or ranked ,which prevents reporting like this.

with thanks & Regards
CS.Kumar

Replies

Bill Guthrie
User offline. Last seen 8 years 42 weeks ago. Offline
Joined: 14 Mar 2005
Posts: 262
weight your activities with resources, that can be points, norms manhours or anything. Then your percent complete will be relative. under autocost rules, Disconnect percent complete with timeframe.Connect percent complete with resources.

cheers bill g.