Converting project planning units

3 replies [Last post]
maurice x
User offline. Last seen 13 years 26 weeks ago. Offline
Joined: 10 Jan 2007
Posts: 4
Hello,

In eed to change a planning setup in hours to a planning in days.

I’ve created a copy with planning unit days and tried to convert the TF and FF Values using export -> divide values by 8 and import, but the FF will not change.

Any suggestions what I can do to convert this project?

Thanks,

Maurice

Replies

maurice x
User offline. Last seen 13 years 26 weeks ago. Offline
Joined: 10 Jan 2007
Posts: 4
Scott,

This part I know, but that doesn’t change the OD/RD/LAG/FF/TF etc.

Maurice
Scott Hastie
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 29 Mar 2005
Posts: 27
Hi there,

you could try copying the project, if you go tools,project utilities,copy.

you should be able to select a planning unit when you are selecting the copy To options. i.e hours, days, weeks, months

Hope this helps.

Scott