Progress Override

3 replies [Last post]
Elizabeth V
User offline. Last seen 17 years 16 weeks ago. Offline
Joined: 14 Nov 2006
Posts: 8
Groups: None
Can someone please tell me where to access the option for "Progress Override". I would also like to know the significance of this option, versus the logic override.

Thank you!

Replies

Elizabeth V
User offline. Last seen 17 years 16 weeks ago. Offline
Joined: 14 Nov 2006
Posts: 8
Groups: None
Thank you so much! That article is very informative.
Dayanidhi Dhandapany
User offline. Last seen 3 years 48 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
Hi Elizabeth,

It is not logic override, that is retained logic, anyhow to access progress over ride, go to Tools->Schedule(Don’t press F9)->Options->look for progress override to check that option under the item when scheduling activities apply.

remaining things look for the other post.
Karim Mounir
User offline. Last seen 10 years 29 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
Hi Elizabeth,

You can checkout this address for more information about Retained Logic & Progress Override:
http://www.pmicos.org/topics/aug2003.asp

And You can choose the method of scheduling from:
"Tools"-->"Schedule"-->"Options"

Regards.