Progress Override

E
Elizabeth V 👤 Member for 19 years 7 months
D
Dayanidhi Dhandapany 👤 Member for 23 years 3 months

Hi Elizabeth,



It is not logic override, that is retained logic, anyhow to access progress over ride, go to Tools->Schedule(Don’t press F9)->Options->look for progress override to check that option under the item when scheduling activities apply.



remaining things look for the other post.

Forum Sponsor

Top Posters

JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts