Progress Override
Forum Sponsor
Top Posters
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Thank you so much! That article is very informative.
Hi Elizabeth,
It is not logic override, that is retained logic, anyhow to access progress over ride, go to Tools->Schedule(Don’t press F9)->Options->look for progress override to check that option under the item when scheduling activities apply.
remaining things look for the other post.
Hi Elizabeth,
You can checkout this address for more information about Retained Logic & Progress Override:
http://www.pmicos.org/topics/aug2003.asp
And You can choose the method of scheduling from:
"Tools"-->"Schedule"-->"Options"
Regards.