Record actual quantities

2 replies [Last post]
Eckart Schenck
User offline. Last seen 5 years 1 week ago. Offline
Joined: 25 May 2005
Posts: 28
Groups: None
Hi,

The activities in my schedule are loaded with different resources (up to 3 resources per activity).
For recording progress by actual quantities I’m looking for a way to do it by importing from excel (using wk1).

example:
- activity: electrical installation
- Resources: Cable Tray, Cable, Panel

Esp. which headers do I need for the columns of the .wk1 file. I couldn’t figure it out from exporting.

Any idea/help will be very appreciated!

cheers

Replies

Jose Frade
User offline. Last seen 3 years 51 weeks ago. Offline
Joined: 7 Jun 2005
Posts: 144
Groups: None
Hello Heinz,

Take a look in RA and you will find all you need.

Note: RA is distributed with Primavera but not installed automatically from the CD.

You have to locate the RA directory in the CD and copy it into the P3WIN directory in you computer.

You have samples to use in Excell, Acesss, etc.

BR
JMFrade
David Kelly
User offline. Last seen 2 years 30 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
Heinz,

Because the index of the resouce assignment table is resource AND cost account, it is important that you export both of these columns when creating your template.

Given that you can import either "this period" or "to date" manhours the actual hours field you export/import is important, as is the setting "link actual and to date" in the autocost rules.