Finish Constraint And Budgeted Quantity

No replies
Steve Waack
User offline. Last seen 18 years 16 weeks ago. Offline
Joined: 10 Aug 2006
Posts: 3
Groups: None
Once your data date is greater than your expected finish date, the duration is zeroed, and the budgeted quantity is zeroed. Is there an autocost rule to leave the bugeted quantity at it’s assigned value and not zero it out?