Dear fellow members,
We are doing certain Turnkey projects.
One of the serious issues I am facing is to produce a resource driven schedule.
2 days ago my manager asked me to make a resource driven schedule for Power Cable laying works in which Kilometers of Cable will be laid in specially arranged trenches.
My question is,
I have a few activities called cable laying. One of the key predecessor activities is Cable Delivery from a foreign country.
Let the activities as below,
Activities Duration Budg.Qty
1.Cable Delivery Lot-1 1 day 2.5Km
2.Cable Laying -1 5 0.9 Km FS-1
3.Cable Laying-2 5 0.9 Km FS-2,1
4.Cable Laying -3 5 0.9 Km FS 3,1
I need to assign the Resource called “Cable-Lot 1” to the first activity (No.1) as driving with a Budgeted Qty of 2.5 KM. What should be the normal and maximum limit in the resource definition?
Please guide me, How can I use the same resource for the following 3 activities.
More precisely, I have already assigned the resource to the first activity with B.Q. I want to use the 2.5 KM Cable for the following 3 activities with BQ of 0.9 Kms each.
How can I assign the same resource to these activities as driving?. How will the primavera identify the total 2.5 KM cables are for the following 3 activities?
Because you can see, the total estimated qty for 3 cable laying activities is 2.7 KM.How will the primavera identify the need of excess qty in order to schedule the 3rd activity.?
With this data how can I make a sample resource driven schedule with proper resource assignment?
I hope you understand my question. Please find attached the sample file which I made in primavera.I was getting difficulty doing the resource assignment including inputting the budgeted quantities.P3 was not accepting the values.when I tried to schedule it, activity durations became zero for one or two activities.
Kindly kelp me.
Many thanks
Renju