using actual dates in relationships

3 replies [Last post]
ALPER TUFAN
User offline. Last seen 15 years 12 weeks ago. Offline
Joined: 6 Jun 2006
Posts: 4
Groups: None
my question is about the relationships between activities.i want to link some of the activities with SS+lag not only using the early start dates but also the actual start dates..how can i manage this in p3..
or is it possible to use the actual dates for linking activities?
thanks...

Replies

ALPER TUFAN
User offline. Last seen 15 years 12 weeks ago. Offline
Joined: 6 Jun 2006
Posts: 4
Groups: None
thank you all..

regards..
Ronald Winter
User offline. Last seen 3 years 50 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
Look under Tools / Schedule / Options / General. There you will find the option, "Calculate start-to-start lag from:". Your options are early start & actual start. Good luck!
Sukumaran Subaram...
User offline. Last seen 9 years 32 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
Actual means it is already happen and past. Now the activities are considered as As-Built.

You can add or reduce the lag to current and future activities only, i.e. after the data date.

Regards.