But how can anyone Claim for the cost of material on Site As so many principal material having the cost 90 % of the work ..just like AC Machine( FCU) with primavera
P3 can also directly generate monthly payment report, if & when specified in the contract. The utility is available (report writer, etc.). Another way is to download the progress data from P3 then work the payment report either in spreadsheet or database programs.
Naturally the schedule has to be contract cost loaded to be able do that.
Very often contracts prices are broken down with a certain type of division.
To create the structure of the database where you also consider this contract structure will help to sort activities and summarise progress as per contract.
For the format of the report the suggestion of Daya to liase with consultant/client is normaly used.
BR
JMFrade
Member for
22 years 7 months
Member for22 years7 months
Submitted by Dayanidhi Dhandapany on Wed, 2006-04-19 07:51
You can check with your contractual requirement for preparation of Monthly Payment Reports, if nothing can be found about the details of it, liaise with the consultant for the format.
Member for
20 years 5 monthsRE: Preparation of Monthly Payment Report?
U may go this way!
1)Create under resource list; all the BOQ items or if it is lump sump then also assume some suitable quantities and assign the rate.
2) assign all the BOQ items to the corresponding activities.
3) Update frequently then when u schedule:all the actual qnt completed within that period in p3.
4) Use actual this period option of P3 this will give u better result.
5)and finally generate the payment report by filtering resource related to Boq items.
hope so;
u find it useful
Member for
19 years 8 monthsRE: Preparation of Monthly Payment Report?
To claim the cost of (i.e. FCU) in P3?
(Assuming the contract specify progress billings should be generated from P3):
So simple:
An activity for FCU delivery, with corresponding cost load.
When the unit is delivered, the activity is 100%, bill it.
Member for
20 years 2 monthsRE: Preparation of Monthly Payment Report?
But how can anyone Claim for the cost of material on Site As so many principal material having the cost 90 % of the work ..just like AC Machine( FCU) with primavera
Member for
19 years 8 monthsRE: Preparation of Monthly Payment Report?
Gents,
P3 can also directly generate monthly payment report, if & when specified in the contract. The utility is available (report writer, etc.). Another way is to download the progress data from P3 then work the payment report either in spreadsheet or database programs.
Naturally the schedule has to be contract cost loaded to be able do that.
Rey
Member for
20 years 4 monthsRE: Preparation of Monthly Payment Report?
David,
Very often contracts prices are broken down with a certain type of division.
To create the structure of the database where you also consider this contract structure will help to sort activities and summarise progress as per contract.
For the format of the report the suggestion of Daya to liase with consultant/client is normaly used.
BR
JMFrade
Member for
22 years 7 monthsRE: Preparation of Monthly Payment Report?
You can check with your contractual requirement for preparation of Monthly Payment Reports, if nothing can be found about the details of it, liaise with the consultant for the format.