Resource Planning

10 replies [Last post]
Vinod Nagarahalli
User offline. Last seen 18 years 3 weeks ago. Offline
Joined: 6 Dec 2005
Posts: 17
Hello,

I need to give my clients the resource planeed day wise, now i have uploaded the resource required for each activity in P3, how do i get the out in the following format.
X Axis : Dates
Y Axis : Resources (like Labours, Riggers etc)

Pls help me out.

Regards

Vinod MN

Replies

Hannes de Bruyne
User offline. Last seen 2 years 7 weeks ago. Offline
Joined: 25 Jul 2005
Posts: 154
Groups: None
Thank you,

I must have overseen this button on the format-tab all the time.

Hannes
Christian Adrian ...
User offline. Last seen 5 years 14 weeks ago. Offline
Joined: 3 Jun 2003
Posts: 193
Groups: None
Hello Hannes

There is no "once exported" or "Export" function in the Resource loading.. you could select from the list of reports in it or simply create and modify a report that suits your criteria... you would probably see Resource selection, Format, Selection, Timescale.. customize this according to your needs then to export to excel (just what like Steven said) the data should be exported in csv format..

HTH

Christian
Steven Oliver
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Using Resource Loading as an example, on the format tab, use the option to "Export Report in CSV format". This can then be read by Excel.
Hannes de Bruyne
User offline. Last seen 2 years 7 weeks ago. Offline
Joined: 25 Jul 2005
Posts: 154
Groups: None
Hello Christian

I like to read replies in this forum, because there are still things I can learn after many years of P3. What would be interesting is what you do between

"tabular or loading..." and "once exported" because here I don’t find a function called "Export"

thanks
Hannes

Vinod Nagarahalli
User offline. Last seen 18 years 3 weeks ago. Offline
Joined: 6 Dec 2005
Posts: 17
Thx
It worked.


Vinod
Vinod Nagarahalli
User offline. Last seen 18 years 3 weeks ago. Offline
Joined: 6 Dec 2005
Posts: 17
Thx
It worked.


Vinod
Christian Adrian ...
User offline. Last seen 5 years 14 weeks ago. Offline
Joined: 3 Jun 2003
Posts: 193
Groups: None
To export to excel try.. tools> tabular reports> Resource> tabular or loading... once exported it’s up to your imagination to do the rest...

Cheers!

Christian
Vinod Nagarahalli
User offline. Last seen 18 years 3 weeks ago. Offline
Joined: 6 Dec 2005
Posts: 17
Hello,
How do i export the resource table preview to excel?


Vinod
Vinod Nagarahalli
User offline. Last seen 18 years 3 weeks ago. Offline
Joined: 6 Dec 2005
Posts: 17
Hello,
How do i export the resource table preview to excel?


Vinod
Christian Adrian ...
User offline. Last seen 5 years 14 weeks ago. Offline
Joined: 3 Jun 2003
Posts: 193
Groups: None
You could preview it onsceen by pressing shit+F7 or ctrl+F7 then you can select whichever resource you would like to see (Graphical or tabular)... or you could run a graphical report in P3 or may export the resource data in excel and create the XY graph you want...

HTH

Christian