Resource Percent Complete

3 replies [Last post]
Amar Aghana
User offline. Last seen 17 years 15 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 103
Hi Guys,

I want to run a global change to show Resource Percent Complete (RCP) equal to Percent Complete(PCT)

1) How to create a global change command for this.

I tried RCP EQ PCT

RCP is not a correct command.

2) By entering Resource Percent Complete (RCP)also while updating, I hope we will be projecting resource requirement correctly for the balance period.

Please advise.

Replies

Yves Trudel
User offline. Last seen 17 years 47 weeks ago. Offline
Joined: 30 Jul 2005
Posts: 33
Groups: None
Yes I use Primavera 3.1
What I am suggesting is really to put these expected finish dates only on activities that have an actual start, meaning that I have a strong reference to foresee their finish dates.
It prevents me to be obliged to bring back their end dates after moving the data date. When you have large quantities of activities to update every week, I still believe that this could ease the planner job.
I hope I will find some supporters!
;-)
YVes
Bill Guthrie
User offline. Last seen 8 years 28 weeks ago. Offline
Joined: 14 Mar 2005
Posts: 262
check your autocost rules set up

bill
Yves Trudel
User offline. Last seen 17 years 47 weeks ago. Offline
Joined: 30 Jul 2005
Posts: 33
Groups: None
Use RPCT equals PCT
Yves Trudel