EV uses budget from current or target project?

2 replies [Last post]
Vanessa Morris
User offline. Last seen 19 years 20 weeks ago. Offline
Joined: 4 Jul 2005
Posts: 13
Hi, in Tools->Options->Earned Value, P3 asks "when calculating earned and planned values, use the budget from?", and then gives two options: 1) Current project, 2) Target Project. By default, the current project is selected. Theory says that we use current projects and target projects in order to measure performance. So, if we are going to use current project and not the target, isn’t this a contradiction? shouldn’t the target project be selected by default? If the target project is not selected, then why do we create one? I’ll wait for the comments of the experts. Thank you.

Replies

Zq qz
User offline. Last seen 13 years 5 weeks ago. Offline
Joined: 6 Jun 2003
Posts: 163
Groups: None
Vanessa your right...........
Vanessa,

I have used this option when after baselining a schedule I have entered unapproved variations into the current schedule, with a budget. I then have the option to establish the earned value based on original scope (Target1) or current scope plus unapproved variations(current). In the real world variations can progress before approval (although again theory tells us this is taboo).

There are a lot of schedules that I have come across as a consultant that have no baselines. I suppose what Primavera is also doing is making allowances for those who do not apply a target.

Regards