Resources Assignment

5 replies [Last post]
Renju M
User offline. Last seen 12 years 10 weeks ago. Offline
Joined: 22 May 2005
Posts: 5
Groups: None
Dear friends,

Can anyone explain me the steps to make an activity resource constrained in P3.

Suppose there are 2 activities and the precedence relationship is Start-to-Start.Both the activities wants to use the same resource

For example, ACT1 - Activity 1 - 5d
ACT2 - Activity 2 - 4d - SS ACT1

Resource is JCB with 1 units/MD

How this will affect the scheduling.

Thanks Indeed.

Renju

Replies

Bill Guthrie
User offline. Last seen 8 years 25 weeks ago. Offline
Joined: 14 Mar 2005
Posts: 262
Check your autocost rules set up.
Bill Guthrie
User offline. Last seen 8 years 25 weeks ago. Offline
Joined: 14 Mar 2005
Posts: 262
Assume you are using p3 3.1?
MK TSE
User offline. Last seen 4 years 22 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
You mention the resources per activity is revised. May I know it is: -
- change resources; or
- availble quantity from the pool is revised; or
- budget quantity per activity per resouces revised; or
too many options, please specify.
Vishwas Bindigana...
User offline. Last seen 34 weeks 15 hours ago. Offline
Joined: 24 Apr 2004
Posts: 97
Groups: None
Hi,

Gotta small problem to be solved urgently.

I have a programme of 7000 activities. I have resource-loaded the activities (e.g. Carpenter, Steel Fitter, Mason, Helper, Machine Operator, JCB, Tower Crane, etc.). I make updates on the programme every week. The programme is showing a delay of 15 days. I need the revised resources for the updated activities.

Now here is the problem -
When I generate a Resource-Report, I get the same number of resources per unit time period as of the baseline programme. I’m not interested in the original resource planned before the start of the project. I’m interested in the revised resource required for the updated programme and the project as a whole.

Can anyone advice asap.

Rgds
Frank Borcherdt
User offline. Last seen 7 years 46 weeks ago. Offline
Joined: 3 May 2001
Posts: 88
Groups: None
As you should expect, Act 1 gets the resource first as default priority in the Priorization Tab in levelling is Late Start then Total Float...unless you want to nominate different priorities in which case you can control which resource you wish to get first use of the resource.

HTH