Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

EARNED VALUE

2 replies [Last post]
louise desmond
User offline. Last seen 18 years 46 weeks ago. Offline
Joined: 11 Jan 2005
Posts: 5
Groups: None
Can anybody explain/define what earned value is?

How do you calculate earned value in a programme.

Thankyou.

Replies

Jonathan Kirby
User offline. Last seen 24 weeks 4 days ago. Offline
Joined: 16 Jan 2005
Posts: 41
Groups: None
Louise
You need to get the Estimate/contract price make up for the project and work out the ’value’ of all the activities in your programme. You then can put the value onto each activity. this is easier said than done with many projects as the conntract price breakdown rarely transtates simply into the programme activities. It also requires a sufficiently detailed programme so the value spread on the activity is meaningful.
Once done and early/late date baselines set up, as you progress activities the corresponding Value becomes ’earned’. you can then produce graphs etc of the earned value to as the project progresses, graphs for various selections of activities can also be produced.
This is useful to then compare the earned value against actual costs on the project and monitor your cost to earned value ratio. eg high earned value and low actual cost is good. You can then also make forecasts and projections on the likely end cost.
hope this helps.
JK
Steven Oliver
User offline. Last seen 11 years 39 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Earned Value = Budget Cost of Work Performed (BCWP) and has a very well defined value equivalent to Percent Complete * Budget. At any point in time you should know the budget for an activity, so the hard part is defining % complete.

See Paul Harris’s website for some very good info and application of Ev.


HTH