Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Store Period Performance

20 replies [Last post]
Forum Guest
User offline. Last seen 18 weeks 6 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
hi there,

any one can tell us about this option(sotre period performance)..what it is used for.

is it an option or it is a must

thanks for all particpants in advance.

Ali Hamouda
=============

Replies

Safak Vural
User offline. Last seen 4 years 24 weeks ago. Offline
Joined: 12 May 2008
Posts: 117
Dear Alex,

Thank you for your notice. I was talking about P3.

Regards,

Safak
Alex Wong
User offline. Last seen 11 years 36 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
FYI

If it is P6 you talking about, you can edit your stored PP provided you have the access right

HTH

Regards

Alex

(I use PP to predict the project end date and the 20/80 rule work pretty good)
Mohammad Ajlouni
User offline. Last seen 6 years 18 weeks ago. Offline
Joined: 15 Aug 2009
Posts: 4
Hi Safak,
Thank you a lot for your valuable reply.

I will do the export-import solution and post back the result.

Regards,
Mohammad
Safak Vural
User offline. Last seen 4 years 24 weeks ago. Offline
Joined: 12 May 2008
Posts: 117
Hi Mohhammed,

There is no way to undo stored values in a project. But if you have to undo then i can suggest you to create a new schedule and export-import all data and relations from existing schedule.

Store period performance should be a must if you have an opportunity for a forensic analyses. A good resource loaded and tracked schedule could show what-how the works done months ago with just a few clicks.

The worst nightmare about store perion performance is being seen if you are changing budgets, durations of activities while revising or re-forcaasting schedule. You will have variances and you will need rewrite some resource values or global change a few times to clear the variances. I also encounter import-export problems for percentage completes in P3.

As conclusion it is not a must but it is a should. It isnt must due to : "The best schedule is the schedule you can manage".

Regards,

Safak
Mohammad Ajlouni
User offline. Last seen 6 years 18 weeks ago. Offline
Joined: 15 Aug 2009
Posts: 4
Hi All,
Can you please advice if I can undo this option? Someone have done it on our project (Primavera 6 installed) and we are not aware of how we can remove it now !

Thanks in advance for your help


AJ
Lorenzo Aquino
User offline. Last seen 4 years 44 weeks ago. Offline
Joined: 21 Jul 2003
Posts: 10
Groups: None
RA (SDK)? Sounds new to me. Would you mind to elaborate further.
Dayanidhi Dhandapany
User offline. Last seen 3 years 35 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
you can use P3 Ra (SDK) application to study the things and implement accordingly as per your requirements, anyhow it will take sometime.
Lorenzo Aquino
User offline. Last seen 4 years 44 weeks ago. Offline
Joined: 21 Jul 2003
Posts: 10
Groups: None
If the Stored Period Performance of a certain schedule is done quarterly and let us say we want to switch to store our schedule in monthly or weekly, is there any short way to update considering an available data in spreadsheet. Does "Import" tools is applicable?
Dayanidhi Dhandapany
User offline. Last seen 3 years 35 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
Click this linkfor similar discussion
Alex Wong
User offline. Last seen 11 years 36 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
In order to overcome the 0 actual / unit problem I usually run a global change that impose any resource that had a 0 this period with a $0.1 prior to store period performance, that way it is always correct
Eric Chou
User offline. Last seen 1 year 20 weeks ago. Offline
Joined: 19 Jul 2004
Posts: 29
Groups: None
Attached is the write-up by myself regarding Store Period Peformace. Please review for your reference. Go to the http://www.htcprojectcontrols.com/SB003.pdf Eric Chou, PE HTC Project Controls, Inc.
Dayanidhi Dhandapany
User offline. Last seen 3 years 35 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
sure u can continuously update and store period performance in the same p3 file (for each monthly update). But it is useful if you maintain p3 files separately such ud01, ud02, ud03 for each monthly update. It would be meaningful(filemaintenance) to supply the files to client, u can check for any slippage in time as compared to previous monthly update by keeping ud03 as target for updating progress in ud04, also useful for preparation of disruption analysis as and when required.
Mohammad Kaifi
User offline. Last seen 8 years 28 weeks ago. Offline
Joined: 26 Apr 2003
Posts: 19
Groups: None
If i’ve stored the period performance of activity (say ud01..file)again next time same file i can update.if not then why?
Dayanidhi Dhandapany
User offline. Last seen 3 years 35 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
Dear Ali,

The following procedure will show you the importance of store period performance.

Let us say each monthly update shall be denoted as ud01 (jan), ud02(feb), ud03(mar) for ideal cases.........

Assume some 50 number of foundations in a design unit, you are respresenting it as an activity and loaded with a resource called BQFdn and assigning 50 in Budgeted Quantity.

Assume some foundation works commenced in Feb, say 10 no of foundations completed before the status date of ud02. you update this status in actual to date field by entering 10 and schedule the program. in the next update say ud03(you have to copy ud02 as ud03 first), before statusing the activity(or any activities) you must store the period performance option in ud03 file, then you can notice the actual this period field will show 0 for the foundation activity, which means the number of 10 foundations completed in the previous month has been stored in the database, and ready for fresh-update to display the progress in march(ud03 update), then start to status the activity say another 20 foundations completed, enter the actual to date as 30 and schedule the project(remember again you should not press the store period performance)in ud03 file. so that you can see the historical actual number of foundations completed when you run the s-curve as well early finish date for remaining foundations will be shown in the s-curve.

of course our fellow planners clearly explained about EV............ if you still have some doubt you can use any google search engine to search for EVM concepts.........

hope the above will clarify the importance of store period performance.
Alex Wong
User offline. Last seen 11 years 36 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
EV stand for Earn Value
The progress of work converted to a $ value
ie if the project is budgeted to $10
and if you finished 30% of the job the eared value will be $3
How it help you to track and plan your job
ie if this project is spread over 3 days

after day 1 the project is 30% complete and you spend $5 dollar and day 2 you spend additional $3 and remaining at 30% complete. If you save your period performance every day with P3. you can then plot your ev curve as well as you actual dollar curve and with the data you can then forecast the furture. However, if you do not save the period performance then what happen is you will always have the average of all the past data that means you curve will show day 1 you spend $4 and same as day 2 and you earn $1.5 per days as well. However, this is a misleading information since day 2 you spend $3 and earned $0 if the period is longer than you will see the different.

Forum Guest
User offline. Last seen 18 weeks 6 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
I still don’t understand the function of Store Performance Period.
What is EV?
How’s it help for monitoring purpose?
Can you explain in more detail and simple?

Ali Ham.
Luca Basile
User offline. Last seen 9 years 43 weeks ago. Offline
Joined: 10 Jul 2003
Posts: 288
Groups: TILOS
I had always problems with store period performance, in particular way in big schedule.
I prefer to prepare all the graphs in excel (c-curves, etc ...).
Marc Borburgh
User offline. Last seen 11 years 7 weeks ago. Offline
Joined: 22 Apr 2004
Posts: 55
DOH!
Forum Guest
User offline. Last seen 18 weeks 6 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Store Period Performance function store the actual (Both resource and cost) to a file in the P3 database.

If this is applied for every report period. Then you can have see actual resource/cost usage over time. A better audit trail.

Without it, P3 will spread the resource / cost data linearly between the activity start and finish date only.

Hence you can not see the actual usage overtime.
Marc Borburgh
User offline. Last seen 11 years 7 weeks ago. Offline
Joined: 22 Apr 2004
Posts: 55
It’s an option.

Store period performance will store the EV (quantity & cost) for the datadate you store it on. If you don’t do that, P3 will level out the EV on each task.

Example:

Task takes 10 days with a BQ of 100. After day 5, you are 50%. This means that you have an EV of 10 per day. If you are still 50% after 10 days, you will have a EV of 5 per day! That means that the historic date from the first 5 days will be spread over the 10 days that the task is in progress and thus your progress line will drop in the S-Curve.
If you store period performance, the EV of 50 will remain on the 5 days and the other 5 days that you didn’t earn anything will have a EV of 0 (zero). Your progress line will show the EV of 50 in the first 5 days and a horizontal line the next 5 days.

Hope this is clear enough.