Linking of P3 data base to AutoCad.

1 reply [Last post]
Dayanidhi Dhandapany
User offline. Last seen 3 years 20 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
Dear All,

I would like to pickup activities dates from primavera project planner and incorporate the same into autocad, in order to draw Time-Chainage Diagram. Can anyone help me? in this regard

Thanks in advance
daya

Replies

MK TSE
User offline. Last seen 4 years 11 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
In P3, filter out those activities which will be in chainage diagram by code.

In autocad, prepare a macro including: -
- link to P3 selected activities and look for activity type, duration and dates.
- prepare the axis of the diagram, ie time scale and chainage scale
- shape of each object determine by activity type
- size of the polygon depends by dates and duration
- for color, may by some activity code

MKTSE