Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

"% Complete" - must I press F9 many times?

9 replies [Last post]
P3 Scheduler
User offline. Last seen 20 years 9 weeks ago. Offline
Joined: 16 Feb 2002
Posts: 18
Groups: GPC Malaysia
I have a project which is Organised and Group By "Project" with the "Total" selected in order to show the total % completion for the overall project during each weekly reporting.

During each weekly reporting, I will update the project data and rescheduled the project (by pressing F9) before printing the schedule in pdf file for emailing to my client.

However I noticed that the Project % (% Complete column) shows different percentage value each time I pressed F9 button! The percentage value will only "stabalised" and show consistent value after a few time pressing the F9 button. If I am not carefull I sometime emailed to my client a report which shows incorrect project % completion.

Any clue to what is happening?

Thanks and best regards,
CS Ong

Replies

Forum Guest
User offline. Last seen 10 weeks 11 hours ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
>you are right mr c.s.ong. this i have seen only in pirated
>software of primavera. not with original one. you did not
>tell is it original one or pirated one?

I am using the original version 3.0 but it was an upgrade from V2.0.

Best regards,
csong
Forum Guest
User offline. Last seen 10 weeks 11 hours ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
you are right mr c.s.ong. this i have seen only in pirated software of primavera. not with original one. you did not tell is it original one or pirated one?
MK TSE
User offline. Last seen 4 years 17 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
What type of activity have changing the PCT? Task or others. Just consider the time only, PCT will not change after scheduling (except hammock). If PCT is subject to cost and resouce also, the case is far more complicated.
Jorge Taguinod
User offline. Last seen 2 years 41 weeks ago. Offline
Joined: 8 Jul 2003
Posts: 139
Hi CS Ong,

As I recall in my P3 Basic (601) class, there was this rule about Open Ends in which Primavera strongly advises that there should only be one activity with no predecessor and one with no successor.

This means that all activities with no predecessor should be connected to a dummy activity (start milestone - project start); likewise, all activities with no successor should be connected to a dummy activity (finish milestone - project finish).

I have stuck to this rule and have not experienced your problem. Although I am not sure if this will fix your problem, you may want to try it and inform us of the results.

Good luck.

Best regards,

Jorge
Forum Guest
User offline. Last seen 10 weeks 11 hours ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
I have recently noticed this effect of changing dates and percentages when I used an extensive number of Expected Finish constraints on a large schedule. I had to press the F9 key twice to make all of the constraints ‘take’ before removing then or the dates would change upon recalculation after the dates were removed.

I theorize that the ‘backward’ calculation of remaining duration to meet a certain date is partially the function of previous progress in out-of-sequence activities and retained logic calculation mode. In other words, although an activity has been actually started, if predecessors with remaining duration still exist, the activity in question must delay the resumption of progress until such predecessors are first complete.

This logic ‘pushes’ the start of the remaining duration of the activity started out of sequence. If you add an Expected Finish constraint to this delayed-resumption activity, P3 calculates both ‘ends’ of the activity and they interfere. It appears that pressing the F9 key the first time gets the solution ‘half-right’ and the second calculation finishes the job.

I may be wrong about the theory, but I am sure of the cause and result.
Vincent Tham
User offline. Last seen 18 years 3 weeks ago. Offline
Joined: 20 Apr 2002
Posts: 7
Groups: GPC Malaysia
I agree that what Ali Vessalis comments.

But due to your case, i also encounter it before but finally i solve it. If i not wrong and it may due to your activity linkings and scheduling options problems.

Can you send me a your project file.my e-mail is sducomp@hotmail.com
Ali Vessali
User offline. Last seen 7 years 14 weeks ago. Offline
Joined: 16 Sep 2001
Posts: 55
CS Ong,
I dont understand what is wrong in your schedule. Every time you press F9, P3 will re-calculate all Data such as Percent Complete base on latest update inputs. Note that for calculation of summarization Percent Complete, P3 will use the weighting factor which is set in: Tools/Options/Summarization

In this option you can set the weighting factor by Duration, Resource Unit and Cost. Each time you press F9 the P3 will follow what is set in this option. By defult P3 will calculate the summarization data baseed on Duration.

The resulte of calculated overall percent complete will change if you change the weighting factor. So, it seams that your problem caused by this probebly.
If you need more info. send an E-mail to me (avessali@yahoo.com)
Bye,
Forum Guest
User offline. Last seen 10 weeks 11 hours ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Hi there,

This one is a new one on us. We have mailed this out to the P3 "expert" group.

We will have to wait to see if anyone has a solution.

Regards.
The Planning Planet team.
Se de Leon
User offline. Last seen 3 years 8 weeks ago. Offline
Joined: 15 May 2001
Posts: 321
Groups: None
CSong, I do sometimes also encounter such problem, what I do as a habit, I schedule it 2 times or three times to make sure that the results are consistent. Se