Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Primavera P6 Exercise

No replies
Merty Mac
User offline. Last seen 18 weeks 6 days ago. Offline
Joined: 14 Apr 2023
Posts: 2
Groups: None

Hi All,

I have an exercise that is set around manufacturing (not experienced in Manufacturing) and has a requirement to produce, say, 6 laptops. Each unit is identical in terms of process, i.e. Procure materials, manufacture & assembly, Inspection & testing, then acceptance. 

Question: Would you generally create the schedule for unit/laptop 1 then copy & paste activities  into seperate WBS elements, Unit 2, 3, etc. or just create a simple Unit 2-6 with a start/finish date rather than detailing all remaining units?

Thanks